New Data Centers Go First When the Grid Runs Short
PJM's board proposed on 27 July 2026 that new data centers without their own power get cut first when supply runs short, across 13 states and DC.
Power
Published 30 July 2026 | Last updated 30 July 2026
On 27 July 2026 the board of PJM Interconnection, the largest grid operator in the United States, directed staff to ask federal regulators for a new rule: when there is not enough electricity to go around, new large electricity users that have not brought their own power supply get their consumption cut before the grid reaches for customers who are paid to reduce demand.
The deadline for a new large user to avoid that queue is 1 June 2027. Nothing takes effect until the Federal Energy Regulatory Commission approves it.
The short version
- PJM's board directed two filings to FERC: a one-time capacity purchase, and a service under which new large loads are curtailed first during shortages.
- The cutoff date is 1 June 2027. A new large load that cannot cover its own resource adequacy needs by then falls under the new service.
- Those reductions happen before PJM deploys Pre-Emergency Load Management, the program that pays customers to cut usage.
- New large load demand is projected to rise by about 70 GW by 2038, while roughly 15 GW of generation has retired in PJM since 2022. CLAIM
- Curtailed customers are to be compensated at a FERC-approved rate, but who pays and who qualifies is left to the states.
What is PJM, and where does it operate?
PJM Interconnection is a regional transmission organization, which means it runs the high-voltage grid and the wholesale electricity markets for a large chunk of the eastern United States without owning a single power plant or transmission line. Its job is dispatch and coordination: deciding which generators run, and keeping supply matched to demand.
According to FERC's own description of the market, PJM coordinates wholesale electricity in all or part of 13 states plus the District of Columbia: Delaware, Illinois, Indiana, Kentucky, Maryland, Michigan, New Jersey, North Carolina, Ohio, Pennsylvania, Tennessee, Virginia, and West Virginia. PJM's board letter puts the population served at 67 million. The territory runs to roughly 369,000 square miles per PJM's own fact sheet.
The name is a fossil. PJM began in 1927 as a power pool of three utilities in Pennsylvania and New Jersey, and became the Pennsylvania-New Jersey-Maryland Interconnection in 1956 when two Maryland utilities joined. It now has more than 1,100 members and covers a region that includes Northern Virginia, the densest concentration of data centers on earth.
Does this apply to you?
If you live in one of those 13 states or the District of Columbia, you are inside the system this decision governs. That does not mean your lights are at stake. The point of the proposal is the reverse: PJM is trying to make sure that new large users do not degrade reliability for households and existing businesses, and that existing customers do not pay the capacity costs those new users create.
If you operate or are planning a large facility in the region, the 1 June 2027 date is the one to diary. Under the proposal a new large load that arrives without securing its own supply does not get the same firm service everyone else gets. It gets an interim service, and interim means interruptible.
If you are neither, the part that reaches your bill is the cost allocation, not the curtailment. That thread runs through our earlier reporting on data center costs appearing on power bills and on who actually pays for AI data centers.
What did PJM's board actually decide?
It directed staff to file two separate proposals with FERC by the end of July. The board's decisional letter, signed by chair Paula Conboy, sets out four elements.
A Large Load Registry. Electric Distributors will have to report the location and size of large loads so PJM can forecast demand accurately and administer the two new programs. PJM's newsroom summary defines a large load as a cumulative peak of at least 50 MW at a single site behind one or more delivery points inside a one-mile radius. Registry information becomes public where confidentiality rules allow.
A Reliability Backstop Procurement. A one-time purchase of capacity starting September 2026, targeted at the shortfall from the 2028/2029 Base Residual Auction and reduced by whatever new supply gets contracted privately first. PJM's summary puts the procurement window at 30 September to 21 October, results in early December, commitments running up to 15 years, and a cap of $555 per MW-day on accepted offers, with eligible resources required online no later than 1 June 2032.
An Interim Resource Adequacy Service. This is the curtailment mechanism, and it was called Connect and Manage until this letter renamed it. Electric Distributors must implement it for new large loads that, as of 1 June 2027, do not bring enough capacity to cover their own resource adequacy needs and cannot be served at the 1-in-10 reliability standard, meaning a grid designed to fail no more than once in 10 years. Load reductions under the service occur, in the letter's words, "prior to the deployment of Pre-Emergency Load Management".
Compensation for reduced load. Distributors must implement a FERC-approved compensation rate for large load customers directed to cut consumption, paid on verified performance. Whether a particular large load is entitled to that compensation, or waives it, and which retail customers fund it, is left to state authorities.
Why does the ordering matter more than the date?
Because of what Pre-Emergency Load Management is. It is the program under which customers agree in advance to cut consumption when the grid is stressed, and are paid for doing it. Putting new large loads ahead of that program in the queue means a new data center without its own generation gets reduced before the grid calls on the customers who are being compensated to reduce. In practical terms, the proposal creates a class of electricity user that is first to be turned down and last to be treated as firm. That is a structural change in what connecting to this grid buys you, and it is a bigger fact than any single date.
What did the coverage get wrong?
The story circulated on 28 and 29 July as a decision to cut power to data centers of 50 MW or more starting in June 2027. Three parts of that do not survive the primary document.
| As reported | What the record says | As of |
|---|---|---|
| Curtailment begins June 2027 | 1 June 2027 is the deadline by which a new large load must bring its own capacity. It is a qualifying date, not a start date. | 2026-07-27 |
| Applies to data centers of 50 MW or more | 50 MW is the registry definition of a large load. The service applies to new large loads that have not secured supply, not to existing facilities. | 2026-07-27 |
| PJM will cut off data centers | Electric Distributors are required to implement the service. PJM is proposing the rule, and FERC has not ruled on it. | 2026-07-27 |
| Nowhere. No outlet reviewed covered this. | Curtailed large loads are to be compensated at a FERC-approved rate based on verified performance. | 2026-07-27 |
| Nowhere. No outlet reviewed covered this. | The board rejected a stakeholder proposal that had more than two-thirds sector-weighted member support. | 2026-07-27 |
Reported claims drawn from TechCrunch, 28 July 2026, and Gadget Review, 28 July 2026. Record column drawn from the PJM board decisional letter of 27 July 2026 and PJM's newsroom summary of the same date.
What did the board overrule?
This is the part that went unreported. A coalition proposal for the backstop procurement cleared more than two-thirds sector-weighted member support in the stakeholder vote, and the board declined to file it. Its stated reason was that a voluntary subscription framework gave no assurance that capacity equal to the near-term shortfall would actually be bought. The board acknowledged the proposal had constructive elements and went with a mandatory central procurement instead. Appendix A of the letter lists 13 pieces of correspondence the board received during the process, from state legislators in the PJM footprint, a governors' collaborative, public power entities, consumer advocates, and the utility commissions of West Virginia, Ohio, and Virginia, the last filing jointly with the Data Center Coalition.
Why can PJM not simply bill the data centers?
Jurisdiction. FERC's own guide to the market draws the line: wholesale electricity sales inside PJM cross state lines and FERC sets those rates, while the retail sale from your local utility to your house is not FERC's business. PJM operates on the wholesale side, so it can allocate costs to Load Serving Entities, but it cannot reach through to an individual customer's retail bill.
The board says this directly: because PJM lacks jurisdiction to allocate retail costs to individual data centers, state action will be essential, and PJM will support that by handing states the registry data. So the affordability half of this announcement is a request, not a rule. It also explains why the piece of it PJM can do unilaterally is a forecasting change: the board will exclude incremental new large loads from the demand used in capacity auctions from the 2029/2030 delivery year, so existing customers are not charged for capacity those new loads created. The letter notes that adjustment is for load forecasting purposes only.
What are the dates that matter?
| Date | What happens | As of |
|---|---|---|
| August 2026 | First matches expected in PJM's bilateral contracting process, launched 9 June 2026 | 2026-07-27 |
| 30 Sept to 21 Oct 2026 | Reliability Backstop Procurement runs | 2026-07-27 |
| December 2026 | Procurement results, then the capacity auction for the 2029/2030 delivery year | 2026-07-27 |
| 1 June 2027 | Deadline for a new large load to bring sufficient capacity or fall under the interim service | 2026-07-27 |
| 2029/2030 delivery year | New large loads excluded from auction demand begin re-entering as their own supply is offered | 2026-07-27 |
| 1 June 2032 | Latest online date for resources winning the backstop procurement | 2026-07-27 |
Every date above is a proposal pending FERC review. PROJECTION
How does this connect to what came before?
It is the next step in two threads. In June PJM added a capacity-shortage alert as demand outran supply, which we covered in AI Data Centers Push the Largest US Grid to Shortage Alerts. Separately, FERC ordered six grid operators including PJM to justify or rewrite their rules for connecting large users, covered in FERC Orders Grid Operators to Justify Data Center Connection Rules. This board decision is not PJM's answer to that order. The letter says so in a footnote: the renamed Interim Resource Adequacy Service does not address how load connects to the system, which is the subject of a separate proceeding, Docket No. EL26-67-000.
Sources
- PJM Board of Managers, Board Decisional Letter on Critical Issue Fast Path, 27 July 2026. The four elements, the 1 June 2027 date, the curtailment ordering, compensation, the rejected coalition proposal, the jurisdiction statement, Appendix A.
- PJM Inside Lines, "PJM Board Directs Action on Resource Adequacy, Affordability and Large Loads", 27 July 2026. The 50 MW registry definition, procurement window, $555 per MW-day cap, 15-year commitments, 1 June 2032 online date.
- FERC, PJM market overview, and An Introductory Guide for Participation in PJM Processes. Footprint, history, and the wholesale versus retail jurisdiction line.
- PJM, PJM at a Glance. Territory area and population served.
- PJM Inside Lines, "Stakeholder Process on Backstop Procurement and Connect and Manage Moves Forward", June 2026. The advisory vote on 24 stakeholder proposals.
- Coverage assessed in the record table: TechCrunch and Gadget Review, both 28 July 2026.
Derivations
No figure in this article is derived. Every number is stated by PJM in one of the two 27 July documents, and each is attributed to the document that states it. Where the two documents differ in specificity, the board letter governs.
Open questions
- The size of the 2028/2029 auction shortfall is not in this article. PJM's newsroom summary prints a figure that cannot be correct as published, and the board letter gives no number at all, describing only two successive auctions clearing significantly below the Reliability Requirement. The figure will be carried once it is traced to the auction results themselves.
- The FERC filings themselves had not been docketed at the time of writing. The board directed them by the end of July; the letter is the plan, not the filing.
- A legal alert published after the letter described the shortfall as roughly 60 GW, which matches nothing in either PJM document. Not carried.
- Whether states will act on retail cost allocation, which PJM says is essential and cannot compel.
Corrections policy
AI Race Facts corrects visibly. Errors are fixed here with a dated note, never as silent edits. Figures labeled CLAIM are stated by the named party and not independently audited by this publication. Figures labeled PROJECTION are proposed or forecast, not in effect.
Published 30 July 2026 | Last updated 30 July 2026
Comments
Loading comments…